Project
title: Build a
doghouse for “Tiny,” my
Saint Bernard.
(Level 0 is the project
level; level 1 is the phase level,
etc.)
1 Project
Management (will
overlap all phases of the project)
1.1 Planning (We
will assume Initiating and the Project
Charter are already done)
1.1.1 Scope
Statement
1.1.2 Activity
List
1.1.3 Network
Diagram with Critical Path
1.1.4 Resource
Plan
1.1.5 Time
Estimate
1.1.6 Cost
Estimate
1.1.7 Risk
Analysis with contingencies assigned
during Risk Response Planning
1.1.8 Schedule
1.1.9 Budget
1.1.10 Management
Plans for all areas
1.1.11 Project
Management Plan
1.2 Executing
etc. (This
is not meant to be a complete WBS, just
a sample to give you the idea.)
2 Design
3 Materials
4 Site
Preparation
5 Construction
5.1 Cement
Pad
5.2 Framing
5.3 Walls
5.4 Roof
5.5 Plumbing
5.6 Electrical
5.7 Insulation
5.8
Skylight
5.9 Air
Conditioner Installation
5.10 Jacuzzi
Installation (What do you
mean, “She’s
only a dog???!!!” You obviously
don’t know Tiny!)
5.11 Interior
finishing (paint, wallpaper, fixtures,
etc.)
5.12 Exterior
finishing (siding, etc.)
6 Inspection